K-RIDE invites fresh tenders for Mallige Line civil works after L&T contract termination

Mr. Jindal
3 Min Read

The Rail Infrastructure Development Company (Karnataka) Ltd. (K-RIDE) has invited fresh tenders for the balance civil works of Corridor-2, also known as the Mallige Line, between Benniganahalli and Chikkabanavara.

The project has been split into three separate packages to expedite completion of the long-delayed Bengaluru Suburban Rail Project (BSRP).

The decision comes in the wake of what was termed the ā€˜unilateral and illegal’ termination of contracts for both Corridor-2 (Mallige Line) and Corridor-4 (Kanaka Line) by Larsen and Toubro (L&T), which was the original contractor for the two corridors.

According to K-RIDE officials, the company has now re-invited tenders to complete the pending works of Corridor-2 after the termination by L&T.ā€œThe tenders issued outline specific design and construction scopes for each package,ā€ an official said.

Three packages

Under Package 1, the tender covers the design and construction of an elevated viaduct, including ramps, for a 7.795-km stretch between Benniganahalli and Shettihalli. It also includes the design and construction of a double-decker viaduct with a flyover at Level 1 and BSRP tracks at Level 2, spanning 1.20 km between Lottegollahalli and Yeshwanthpur. This package includes the Mathikere station and the station at Benniganahalli, with a completion deadline of 24 months.

According to the officials, package 2 involves the design and construction of an at-grade section covering 11.569 km between Benniganahalli–Banaswadi and Banaswadi–Hebbal. It includes the station boxes at Nagavara and Kanakanagar, along with the construction of major and minor bridges, road under-bridges (RUBs), and retaining walls. This package has an 18-month completion target.

Meanwhile, Package 3 focuses on the at-grade section between Yeshwanthpur and Chikkabanavara, spanning 5.8 km. It includes an elevated viaduct section of 185 metres and has also been allotted an 18-month deadline.

Decision at board meeting

The decision to float fresh tenders was taken during a K-RIDE Board meeting chaired by the Chief Secretary of Karnataka in October. The Chief Secretary also serves as the Chairman of K-RIDE. The board has authorised the Managing Director to initiate the tender process to ensure that work on the suburban rail project continues without further delay.

The official said, ā€œThe decision follows the advice of the Advocate General of Karnataka, who recommended calling for new tenders even as arbitration proceedings between K-RIDE and L&T continue.ā€

The L&T originally signed contracts with the K-RIDE for Corridor-2 on August 26, 2022, and for Corridor-4 on December 30, 2023. The company was given extended completion deadlines until September 2026 and October 2026, respectively. However, disputes arose over project execution, leading to L&T’s unilateral withdrawal recently.

Share This Article
Leave a Comment